Projected cost of new SEND school in Barnsley more than doubles to nearly £7.4m

Überblick

The projected cost of creating specialist primary school spaces at The Mill at Worsbrough Bridge in Barnsley has more than doubled to nearly £7.4m due to more extensive refurbishment, access works, and specialist equipment requirements than originally anticipated. The school is intended to provide 40 places for children with special educational needs and disabilities, allowing more pupils to learn closer to home. The project will be funded entirely through a ring-fenced government grant.

Wichtige Punkte

  • The projected cost of the specialist primary school project has increased from under £3m to almost £7.4m.
  • The Mill at Worsbrough Bridge is being converted to provide 40 places for children with autism and communication needs, with an expected opening in September 2028.
  • Building and fit-out costs have risen to £3.6m, site entrance and vehicle access costs have risen to £760,000, and fees, overheads, and contingencies total £2.34m.
  • The project is funded entirely by a ring-fenced government grant without requiring council borrowing.
  • Once full, the school is estimated to reduce annual placement and transport costs by £1.6m compared to independent and out-of-borough provision.