HS2 'cut-and-cover' tunnel pieces at Wendover are linked up

Quelle

www.bbc.co.uk

Veröffentlicht am Quelle aktualisiert am (Stand: )

Zu Llamar hinzugefügt am Zusammenfassung aktualisiert am

Originalquelle öffnen (wird in einem neuen Tab geöffnet)
Aerial view of the HS2 green tunnel under construction near Wendover, showing two parallel concrete structures in a deep cutting, with cranes, construction machinery and workers nearby.

Verstehen

HS2 'cut-and-cover' tunnel structure at Wendover completed

Überblick

The central structure of a mile-long 'green tunnel' for HS2 near Wendover, Buckinghamshire, has been completed after 18 months of work. Built using the 'cut-and-cover' method with 2,740 precast concrete segments, the northbound and southbound sections were joined when the final segment was installed.

Wichtige Punkte

  • The mile-long (1.4km) tunnel structure near Wendover is one of five green tunnels on the HS2 route between London and Birmingham.
  • The tunnel was built using the 'cut-and-cover' method, assembling 2,740 precast concrete segments after digging up earth alongside the A413.
  • Work on the structure began in spring 2025 and is carried out by HS2's main works contractor, EKFB.
  • Contractors will now complete the entrances, floor, and internal fittings before covering the structure with earth and landscaping it.