All you need to know about the autumn 2026 Merseyrail closures

Source

www.bbc.co.uk

Published Source updated (as of )

Added to Llamar Summary updated

Open the original source (opens in a new tab)
A yellow Merseyrail train has pulled into a station. Passengers are boarding.

Understand

Merseyrail passengers face month of disruption for tunnel upgrades

Overview

Rail passengers in Liverpool face up to a month of major disruption starting Sunday 11 October as Network Rail and Merseyrail undertake a £3.5m waterproofing and upgrade project on four Victorian-built underground tunnels on the Northern Line. The work aims to reduce power failures and unplanned closures, with normal services resuming on Saturday 7 November.

Key points

  • Merseyrail tunnels on the Northern Line are undergoing a £3.5m waterproofing and upgrade project.
  • The disruption is scheduled to last for 26 days, from Sunday 11 October to Friday 6 November, with services resuming on Saturday 7 November.
  • The Northern Line between Hunts Cross and Liverpool will be closed during the works, with extended disruption to Sandhills and parts of the Wirral line on Sundays.
  • Network Rail is installing new track feeder switches to allow engineers to remotely isolate smaller sections of the railway for faster repairs.
  • Rail replacement buses and amended train services will operate to help passengers complete their journeys.