Tripling of budget for work near River Cam's Jesus Green Lock - BBC News

Source

www.bbc.co.uk

Published Source updated (as of )

Added to Llamar Summary updated

Open the original source (opens in a new tab)
A close-up of a broken piece of concrete bank edging near Jesus Green Lock on the River Cam. Above it is a green verge, and beyond the edging is the Cam, with trees reflected in its water and beyond that the far bank where a boat is moored up.

Understand

Cambridge City Council approves tripling of budget for River Cam wall repairs

Overview

Cambridge City Council has approved an increase in the budget to £2.44m from £850,000 to repair a failing river wall near Jesus Green Lock. The initial estimate assumed work could be done from land, but a full site analysis showed that repairs must be conducted from the river using barges, significantly increasing the cost.

Key points

  • The budget for repairing the river wall near Jesus Green Lock has increased from £850,000 to £2.44m.
  • A section of the wall has been deteriorating and was partially closed in July for safety reasons.
  • Initial cost estimates assumed work could be done from land, but it must instead be carried out using barges from the river.
  • A separate project to repair the nearby lock, closed since May 2024, will be handled by the Conservators of the River Cam.