Hastings line passengers advised to plan ahead for nine-day engineering closure in October

Overview

Rail passengers travelling between Tonbridge and Wadhurst are being urged to plan ahead as the track is scheduled to close for nine days from 24 October to 1 November for essential improvement works. Network Rail is replacing worn slab track inside Grove Hill Tunnel south of Tunbridge Wells, alongside maintenance at several other locations. Replacement buses will operate, and tickets will be accepted on alternative routes.

Key points

  • The line between Tonbridge and Wadhurst will be closed from 24 October to 1 November, extending to Battle on the final day.
  • The primary work involves renewing worn slab track within Grove Hill Tunnel near Tunbridge Wells.
  • Additional improvement works will take place at Wadhurst Tunnel, Stonegate, Etchingham, Robertsbridge and Mountfield Tunnel.
  • Replacement buses will replace trains where services cannot run, and a shuttle train service will operate between Wadhurst and Hastings.
  • Rail tickets will be accepted on alternative high-speed and Southern routes during the closure.